Hello,
Andreas Mueller <address@hidden> writes:
> I just noticed with updated org (org-20170124), although days are no
> longer ignored, the percentage calculation is still wrong.
>
> It looks to me like the problem is that org-effort-durations calculates
> minutes in a day with 8 hours per day (I assume the idea was to only
> plan for 8 hour workdays).
>
> Changing org-effort-durations to calculate with 24 hour days gives the
> correct result of 93% / 7%.
Fixed. Thank you.
Regards,
--
Nicolas Goaziou