On Monday, 11 Sep 2017 at 14:29, Warren Lynn wrote:
> Emacs 24.5.1, Org-mode 9.1, Windows 7
>
> If I have task like this:
> * Spring break
> SCHEDULED: <2018-03-30 Fri>-<2018-04-06 Fri>
>
> I would see "Spring break" listed in the daily agenda for each day between
> the starting and ending date in the "SCHEDULED" line. However, the exported
> ".ics" file only puts one entry for the starting date, which neither
> correctly reflects the task nor be consistent with the daily org agenda
> view.
Not sure whether this helps or not but a period is specified using two
hyphen characters: <...>--<...>
--