Hi; since I was on holiday the 2.3 schedule got a bit lost/delayed.
Discussion on IRC suggests:
2014-03-17: hardfreeze and rc0
2014-03-24: rc1
2014-03-31: rc2
2014-04-07: rc3
2014-04-14: final release
(I've updated http://wiki.qemu.org/Planning/2.3.)
I plan to apply all the outstanding pull requests before the 17th.
We might need to delay rc0 tagging if there are still any particularly
nasty known issues to be squashed.
Remember that we are in softfreeze so don't be too enthusiastic
about pushing new stuff before the 17th :-)
thanks