Carsten Dominik <address@hidden> writes:
> The special property Effort can be used for effort estimates
> ------------------------------------------------------------
>
> If you want to plan your work in a very detailed way, or if
> you need to produce offers with quotations of the estimated
> work effort, you may want to assign effort estimates to
> entries. If you are also clocking your work, you may later
> want to compare the planned effort with the actual working
> time. Effort estimates can now be stored in a special
> property `Effort', displayed side-to-side with clock sums,
> and also be summed over a day, in order to show the planned
> work load of a day. See the manual for more details.
Carsten, I'm already using a property called "Estimate" that works
great, especially in column view. What extra functionally would I get
by switching to this Effort property, or changing the
org-effort-property to work with my Estimate property?
Thanks.
--
Peter Jones, pmade inc.