On Sat, Feb 20, 2010 at 11:28 PM, Nathaniel Flath wrote:
> Hello, using the org-depends package, is there any way to set
> the next task to be scheduled a certain number of days after
> the current one is finished?
not at the moment. though one can visualize the TRIGGER property
chain-siblings-scheduled to be like chain-siblings-scheduled(x) where
x is the number of days to be added to the CLOSED time of the previous
entry to compute new SCHEDULED time. wish i knew sufficient elisp.
--
manish