[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Re: [O] Linked tasks
From: |
Eric Abrahamsen |
Subject: |
Re: [O] Linked tasks |
Date: |
Sat, 14 Jun 2014 16:19:16 +0800 |
User-agent: |
Gnus/5.130012 (Ma Gnus v0.12) Emacs/24.4.50 (gnu/linux) |
Fletcher Charest <address@hidden> writes:
> Dear all,
>
> I was wondering if there was a way to link the status of two tasks in
> an agenda file (or even across multiple agenda files). Sometimes, a
> single task (in my case, updating my CV) might be a useful step in
> two different projects. If the tasks is marked DONE in one project
> (in one subtree), I would like the other one to be marked DONE as
> well. Is it possible or even implemented?
>
> Cheers,
>
> FC
There's an org-depend package in the contrib directory that's supposed
to do this, but I haven't looked at it before... Vanilla Org only does
dependencies within the same subtree.
E
- [O] Linked tasks, Fletcher Charest, 2014/06/14
- Re: [O] Linked tasks,
Eric Abrahamsen <=