Hello,
John Hendy <address@hidden> writes:
> I ran into an error with a 30min task which used the :effort: property
> to set this duration. Upon compilation, I noted the warning:
> ```
> file.tjp:10: Warning: 400.0d of effort of task one does not fit into
> the project time frame.
> Warning: 1 tasks could not be scheduled
> ```
>
> I looked at the .tjp file, and 30min had been converted to 4800.0
> hours. I was able to reproduce with the following setup:
>
> #+begin_src min-config
> (add-to-list 'load-path "~/.elisp/org.git/contrib/lisp/")
> (require 'ox-taskjuggler)
> #+end_src
>
> emacs -Q M-x load-file ~/path/to/min-config
>
> #+begin_src tj-time-test.org
>
> * Project :taskjuggler_project:
> ** task1-effort-min
> :PROPERTIES:
> :start: 2014-11-01
> :effort: 30min
> :allocate: jwhendy
> :END:
> ** task2-duration-min
> :PROPERTIES:
> :duration: 30min
> :allocate: jwhendy
> :blocker: previous-sibling
> :END:
>
> #+end_src
>
EFFORT is a special property in Org (i.e., it is not specific to
taskjuggler). It expects "HH:MM" format. So, you should set it to
:Effort: 00:30
Regards,
--
Nicolas Goaziou