After assigning an effort estimate to a task, you can filter all tasks with an estimate less-than, equal-to, or greater-than a specified number of minutes using org-agenda-filter-by-effort (press the "_" key when viewing the agenda).
On 06/04/18 20:32, Cecil Westerhof wrote:
Is it possible to schedule a task on a day without a time, but have a duration?I have several tasks that are not bound to a time, but will be done when I have some spare time. It would be handy if there was a way the estimated duration of those tasks so I can choose the right one.And in general I find it useful to see how much work there still is to be done.-- Cecil Westerhof