columnview dynamic block - different time summing behaviour for EFFORT a


From: Alexander Adolf
Subject: columnview dynamic block - different time summing behaviour for EFFORT and CLOCKSUM
Date: Mon, 08 Apr 2024 23:08:15 +0200

Hello Org experts,

it seems that the time summing behaviour of columnview dynamic blocks is
different for CLOCKSUM than for EFFORT columns with respect to how the
contributions from sub-headlines are handled. When summing up CLOCKSUM
columns, a parent headline can have its own clocked time, which gets
added to the sum of its sub-items' clocked times to produce its CLOCKSUM
value. When summing up EFFORT columns, any effort a parent headline may
have been manually assigned gets overwritten with the sum of its
sub-items' efforts, however. In the example at the end of this message,
compare the results for tasks A and D. If you change the effort for
either task B or C, and then update the dynamic block, the EFFORT in the
property drawer of task A will get overwritten with the new sum of B's
and C's efforts.

I'd have two questions regarding this:

Does anyone recall the rationale for this different behaviour?

Is there any way to change the summation behaviour for either or both
column types?


I have no preference for either behaviour; they both will have their
merits and applications, depending on how one organises things. I do
think that being able to get the same behaviour would seem advantageous,
however.


Many thanks and looking forward to your thoughts,

  --alexander


---------------------------- Begin Quote -----------------------------
* Example Project
#+BEGIN: columnview :maxlevel 4 :skip-empty-rows t :indent t :format 
"%70ITEM(Task) %17Effort(Estimated){:} %17CLOCKSUM(Clocked){:}" :id local
| Task            | Estimated | Clocked  |
|-----------------+-----------+----------|
| Example Project |   6d 0:00 | 15d 0:00 |
| \_  Task A      |   3d 0:00 | 9d 0:00  |
| \_    Task B    |        1d | 3d 0:00  |
| \_    Task C    |        2d | 3d 0:00  |
| \_  Task D      |   3d 0:00 | 6d 0:00  |
| \_    Task E    |        1d | 3d 0:00  |
| \_    Task F    |        2d | 3d 0:00  |
#+END:
** Task A
:PROPERTIES:
:EFFORT:   3d 0:00
:END:
:LOGBOOK:
CLOCK: [2023-12-08 Fri 15:51 +0100]--[2023-12-09 Sat 01:50 +0100] =>  9:59
CLOCK: [2022-01-07 Fri 18:35 +0100]--[2022-01-08 Sat 08:36 +0100] => 14:10
:END:
*** Task B
:PROPERTIES:
:Effort:   1d
:END:
:LOGBOOK:
CLOCK: [2023-12-08 Fri 15:51 +0100]--[2023-12-09 Sat 01:50 +0100] =>  9:59
CLOCK: [2022-01-07 Fri 18:35 +0100]--[2022-01-08 Sat 08:36 +0100] => 14:10
:END:
*** Task C
:PROPERTIES:
:Effort:   2d
:END:
:LOGBOOK:
CLOCK: [2023-12-08 Fri 15:51 +0100]--[2023-12-09 Sat 01:50 +0100] =>  9:59
CLOCK: [2022-01-07 Fri 18:35 +0100]--[2022-01-08 Sat 08:36 +0100] => 14:10
:END:
** Task D
*** Task E
:PROPERTIES:
:Effort:   1d
:END:
:LOGBOOK:
CLOCK: [2023-12-08 Fri 15:51 +0100]--[2023-12-09 Sat 01:50 +0100] =>  9:59
CLOCK: [2022-01-07 Fri 18:35 +0100]--[2022-01-08 Sat 08:36 +0100] => 14:10
:END:
*** Task F
:PROPERTIES:
:Effort:   2d
:END:
:LOGBOOK:
CLOCK: [2023-12-08 Fri 15:51 +0100]--[2023-12-09 Sat 01:50 +0100] =>  9:59
CLOCK: [2022-01-07 Fri 18:35 +0100]--[2022-01-08 Sat 08:36 +0100] => 14:10
:END:
----------------------------- End Quote ------------------------------