| From: | Noli Sicad |
| Subject: | Re: [Help-glpk] MIP Solvers (i.e CBC, CPLEX, GLPK, GUROBI, LPSOLVE, SCIPC, SCIPL, SCIPS and XPRESS) Benchmark |
| Date: | Mon, 19 Nov 2012 18:30:08 +1100 |
Hi Andrew,
> Looks like your instance is maximization while mps always assumes
> minimization. You need either to change the objective sign in the
> mathprog model or specify --max option for glpsol.
I don't understand this statement. Where do you "specify -max option
for glpsol"?
e.g. glpsol --math TimberHarvestModel_0025p.mod --wfreemps
TimberHarvestM_freemps.mps
The objective function of the MatProg model is already maximize.
e.g.
maximize Discounted_Net_Value:
sum {s in STAND, p in PERIOD} Stand_Cut_Candidates[s,p] *
NPV_Calc[s,p] * FStand[s,p];
Noli
| [Prev in Thread] | Current Thread | [Next in Thread] |